The landscape at John S. Rainey Generating Station is changing day by day. From massive concrete foundations to towering cranes lifting heavy machinery, our landmark expansion project is moving full steam ahead. Santee Cooper is expanding the plant to support South Carolina’s rapid growth, while continuing to deliver reliable and highly efficient energy.
Here is a look at the progress we have made on-site, a deep dive into the heavy machinery driving this expansion and a sneak peek at the highly anticipated milestones just around the corner.

At its core, the combined-cycle conversion project is about optimizing what we already have. The team is converting two existing simple-cycle units into an integrated, highly efficient combined-cycle system. By capturing and repurposing the high-temperature waste heat that currently escapes from these units, we are adding approximately 184 megawatts (MW) of capacity to the grid.
This provides a massive capacity boost to the grid without requiring additional natural gas and without increasing the station’s overall emission rate. It also showcases a significant step forward in sustainable energy production, as we can generate more baseload power while maintaining our commitment to environmental stewardship.
Beyond grid reliability, this three-year project drives local economic growth by bringing roughly 300 skilled construction jobs to the region during peak activity.
Before the massive steel structures could rise, the groundwork had to be flawless. Our journey started last year.

Nov. to Dec. 2025
Massive Concrete Foundation Pours
Why It Matters:
Creates a heavy-duty base to support multi-ton equipment, such as the Heat Recovery Steam Generator (HRSG).

May 2026
“Tabletop” Concrete Platform Pours
Why It Matters:
This is a specialized, ultra-stable platform designed to safely absorb high-vibration machinery, such as generating units.

June 2026
Cooling Tower Construction Begins
Why It Matters:
This new state-of-the-art cooling tower is an essential component for managing the station’s thermal efficiency.
With critical foundation work done, the site was ready for two major pieces of equipment: the condenser and Heat Recovery Steam Generator (HRSG).
The Unsung Hero of the System
The project reached an exciting new phase in July with the arrival and construction of the station’s new steam surface condenser. The condenser is the unsung hero of a combined-cycle power plant. Its job is to take the exhaust steam from the turbine and cool it back down into water, which can then be pumped back into the boiler to start the cycle all over again. By creating a continuous closed loop, it maximizes efficiency and conserves water resources.
The sheer logistics of delivering the massive condenser components to the site required months of planning. Once onsite, our rigging and construction crews worked tirelessly to precisely position, secure and assemble the unit.
The HRSG Takes Shape
If the condenser is the cooling heart of our system, the HRSG is the engine of our efficiency gains.
In a combined-cycle plant, the HRSG captures hot exhaust gas from the gas turbine, heat that would otherwise be wasted, and uses it to generate superheated steam. This steam is then directed to a steam turbine to generate additional electricity without burning any extra fuel. Following our foundational concrete pours last winter, the assembly of the HRSG marked a period of rapid progress onsite.
Crews worked through early September to complete the assembly of the towering HRSG structures, which stand over 100 feet tall. Later that month, the team successfully lifted and placed the massive steam drums into position atop the completed towers, finalizing the core of the new unit.
While we celebrate how far we have come, we are already preparing for the next phase of expansion, which is the delivery of the Steam Turbine Generator (STG).
Scheduled to arrive later this fall, the STG is the powerhouse component that will convert the steam produced by the HRSG into emissions-free electricity.
Given its immense weight and precise engineering, the arrival, offloading and installation of the STG will be one of the most technically demanding phases of the entire project. The team is already preparing the foundation and coordinating the complex transport logistics.
As each new piece of machinery locks into place, Santee Cooper moves one step closer to delivering an even stronger, more sustainable grid for the communities we serve. Milestones like these aren’t just dates on a calendar. They represent thousands of hours of planning, engineering, manual labor and an unwavering commitment to safety.